FirstEnergy Subsidiary To Purchase Natural Gas Combined-Cycle Plant in Northwest Ohio
AKRON, Ohio, Jan. 29 /PRNewswire-FirstCall/ -- FirstEnergy Corp. subsidiary FirstEnergy Generation Corp. was the winning bidder in an auction of a partially complete, 707-megawatt (MW) natural gas, combined- cycle generating plant in Fremont, Ohio. The facility, formerly known as Fremont Energy Center LLC, will be purchased from Calpine Corporation for $253.6 million under a definitive purchase agreement signed yesterday, pending approval of the United States Bankruptcy Court, Southern District of New York.
"The Fremont facility has significant value to us because it is located in an area where we currently serve customers and it is connected to two regional transmission organizations - the Midwest Independent Transmission System Operator and the PJM Interconnection," said Richard R. Grigg, executive vice president and Chief Operating Officer of FirstEnergy. "Adding this plant to our fleet further diversifies our generation mix and, because of its low- emitting characteristics, will further reduce our average carbon-dioxide emission rate, which already is about one-third below the regional average."
Construction of the facility - which includes two combined-cycle combustion turbines and a steam turbine capable of producing 544 MW of load- following capacity and 163 MW of peaking capacity - began in September 2001. In court documents, Calpine has indicated that the plant is about 70 percent complete and could take 12 to 18 months and approximately $150 million to become operational. However, FirstEnergy has not yet completed its engineering review, which will finalize the cost and the timeframe for construction.
FirstEnergy is a diversified energy company headquartered in Akron, Ohio. Its subsidiaries and affiliates are involved in the generation, transmission and distribution of electricity, as well as energy management and other energy-related services. Its seven electric utility operating companies comprise the nation's fifth largest investor-owned electric system, based on 4.5 million customers served within a 36,100-square-mile area of Ohio, Pennsylvania and New Jersey; and its generation subsidiaries control more than 14,000 megawatts of capacity.
Forward-Looking Statements: This news release includes forward-looking statements based on information currently available to management. Such statements are subject to certain risks and uncertainties. These statements include declarations regarding our, or our management's, intents, beliefs and current expectations. These statements typically contain, but are not limited to, the terms "anticipate," "potential," "expect," "believe," "estimate" and similar words. Forward-looking statements involve estimates, assumptions, known and unknown risks, uncertainties and other factors that may cause our actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements. Actual results may differ materially due to the speed and nature of increased competition in the electric utility industry and legislative and regulatory changes affecting how generation rates will be determined following the expiration of existing rate plans in Ohio and Pennsylvania, economic or weather conditions affecting future sales and margins, changes in markets for energy services, changing energy and commodity market prices, replacement power costs being higher than anticipated or inadequately hedged, the continued ability of FirstEnergy's regulated utilities to collect transition and other charges or to recover increased transmission costs, maintenance costs being higher than anticipated, other legislative and regulatory changes including revised environmental requirements, the uncertainty of the timing and amounts of the capital expenditures needed to, among other things, implement the Air Quality Compliance Plan (including that such amounts could be higher than anticipated) or levels of emission reductions related to the Consent Decree resolving the New Source Review litigation or other potential regulatory initiatives, adverse regulatory or legal decisions and outcomes (including, but not limited to, the revocation of necessary licenses or operating permits and oversight by the Nuclear Regulatory Commission including, but not limited to, the Demand for Information issued to FENOC on May 14, 2007) as disclosed in our SEC filings, the timing and outcome of various proceedings before the PUCO (including, but not limited to, the Distribution Rate Cases and the generation supply plan filing for the Ohio Companies and the successful resolution of the issues remanded to the PUCO by the Supreme Court of Ohio regarding the Rate Stabilization Plan and the Rate Certainty Plan, including the deferral of fuel costs) and the PPUC (including the resolution of the Petitions for Review filed with the Commonwealth Court of Pennsylvania with respect to the transition rate plan for Met-Ed and Penelec), the continuing availability of generating units and their ability to continue to operate at or near full capacity, the ability to comply with applicable state and federal reliability standards, the inability to accomplish or realize anticipated benefits from strategic goals (including employee workforce initiatives), the ability to improve electric commodity margins and to experience growth in the distribution business, the ability to access the public securities and other capital markets and the cost of such capital, the outcome, cost and other effects of present and potential legal and administrative proceedings and claims related to the August 14, 2003 regional power outage, the risks and other factors discussed from time to time in our SEC filings, and other similar factors. The foregoing review of factors should not be construed as exhaustive. New factors emerge from time to time, and it is not possible for us to predict all such factors, nor can we assess the impact of any such factor on our business or the extent to which any factor, or combination of factors, may cause results to differ materially from those contained in any forward-looking statements. We expressly disclaim any current intention to update any forward-looking statements contained herein as a result of new information, future events, or otherwise.
Wenn Sie mehr über das Thema Aktien erfahren wollen, finden Sie in unserem Ratgeber viele interessante Artikel dazu!
Jetzt informieren!
Nachrichten zu FirstEnergy Corpmehr Nachrichten
Analysen zu FirstEnergy Corpmehr Analysen
Aktien in diesem Artikel
FirstEnergy Corp | 40,20 | 0,00% |
Indizes in diesem Artikel
S&P 500 | 6 032,38 | 0,56% |