New York, April 07, 2015 -- On 7 April 2015, the Georgia Public Service Commission (GPSC) denied Georgia Power Company's (A3 stable) request to amend by August the certificate of convenience and necessity it granted for the Vogtle new nuclear construction project to reflect the higher cost estimates and revised schedule recently provided by the construction contractors. Instead, the GPSC will take no action on the request until after the completion of the first of the two new units (Unit 3), which the revised schedule has pushed back by 18 months to the second quarter of 2019 and could be delayed further.